How to build a production plan: from customer order to a shift on the line
A production plan answers one question: what gets made, on which line, on which day and in which shift, so the goods are ready for loading. Step by step, with an example: from demand and loading dates, through the bill of materials and material availability, to releasing work orders to the warehouse and comparing plan with actuals.
In short
- A production plan answers four questions — what gets made, on which line, on which day and in which shift — and derives all of them from the customer’s loading date.
- The production day is scheduled backwards: subtract the time the product needs before loading from the loading date, counting working days only.
- Before a job gets a slot on a line, the bill of materials has to show that raw materials and packaging arrive in time — day by day, not for the month as a whole.
- A work order becomes real when it reaches the warehouse; actual consumption and output come back from the warehouse and sit next to the plan, with no manual entry.
- In NG Operations a wizard turns customer orders into production orders, and the plan is arranged with drag and drop on a line × day × shift grid.
Short answer: you build a production plan backwards, starting from the day the goods have to be loaded for the customer. Collect demand from orders and contracts, subtract from each loading date the time the product needs before loading, and you have the production day. Then check through the bill of materials that raw materials and packaging arrive in time, assign the work to a line, a day and a shift, tell sales when you can deliver, and release the work orders to the warehouse. Finally, compare the plan with what the warehouse actually issued and received. Each step is below, with an illustrative example.
What a production plan has to say
A production plan is not a list of quantities for the month. It is a schedule that answers four questions: what gets made, on which line, on which day and in which shift. When one of them goes unanswered, someone else makes the call — the shift lead in the morning, a warehouse operator who doesn’t know what to prepare, or a salesperson who promises the customer a date on gut feeling.
For most plants, planning by shift is the right level of detail: precise enough for the warehouse to know when to stage material, and simple enough that the plan doesn’t need reworking after every small change. A good plan has two more properties. Every job in it is tied to a customer order, so you know who you are making it for. And every job has been checked for material, so you know the line won’t stop.
Step 1: collect demand and loading dates
The plan starts from demand, not from line capacity. Three sources are worth looking at together:
- Customer orders — firm quantities with a loading date. They are the backbone of the plan.
- Contracts — what has been agreed but not yet ordered. Not tomorrow’s work, but it shows what is coming and what purchasing has to anticipate.
- The loading calendar — how many loadings are already booked on each day. If a day is full, a new order shouldn’t land on it just because the customer asked.
The single most important data point is the loading date. It sets the production day, it tells purchasing when material must be in the warehouse, and it is what the customer uses to judge whether you kept your promise. An order with a wrong or missing loading date causes an error in every step that follows.
In NG Operations customer orders are entered by hand or imported from Excel, and sales planning places them on the loading plan — a calendar where you change a loading date by dragging the order to another day.
Step 2: work back from the loading date to the production day
Goods are rarely loaded on the day they are made. Between production and loading there is usually chilling or freezing, a lab analysis, palletising, or simply a buffer in case something goes wrong. So the production day is scheduled backwards: the loading date minus the number of days the product needs before loading.
That offset is not the same for every product: one that waits for a lab result needs more time than one that can go straight onto the truck. Only working days count. If the plant doesn’t work on Sundays and public holidays, no job may fall on those days, and a job that starts before the weekend continues in the first shift after it.
In NG Operations a wizard that builds the plan from orders does exactly this: for a chosen loading period it reads the orders, subtracts the set number of days from each loading date, proposes the production day and spreads the production orders across shifts. The company’s non-working-day calendar — rules per weekday plus public holidays — applies throughout, so an order that runs over several shifts skips weekends and holidays on its own.
Step 3: check materials before you take up a line
A job placed on a line without the material to run it is not a plan — it’s a wish. Before scheduling, explode the demand through the bill of materials: how much of each raw material, consumable and packaging item every product needs, plus the allowance for loss and scrap. Then compare that requirement with what exists or is on its way:
- stock in the warehouse,
- goods in transit,
- open purchase orders with suppliers,
- material already issued to production for the same orders.
Whatever is left is the shortage — and it has to be per day, because film missing for Monday is a different problem from film missing at the end of the month. Packaging is a frequent cause of stoppages here, since a box or label made for one customer can’t be borrowed from another order. How to plan it is covered in Packaging planning in manufacturing.
In NG Operations the raw-material and packaging planning screens calculate the daily shortage from the same orders and bills of materials the production plan is built from, and material requirements planning turns it into purchase orders with one wizard. Purchasing and production work from the same number.
Step 4: assign work to line, day and shift
Only once dates and materials are clear does work go onto the lines. The plan is easiest to read as a grid: rows are lines, columns are days, and each day is split into shifts I, II and III. Each entry in the grid is a work order — one product, a set quantity, one line, day and shift. Three rules make such a plan workable:
- A job takes as many shifts as it really takes. The planner knows what a line gets through in a shift; a large job occupies several consecutive shifts rather than being squeezed into one.
- Large jobs are split by quantity. When one line can’t keep up, part of the quantity moves to another shift, another day or another line.
- Unplanned work must stay visible. Everything ordered but not yet scheduled sits on its own list until it gets a slot.
That is how the production plan works in NG Operations. A customer order becomes a production order, and the production order becomes work orders, one per product. Unplanned work is dragged from its own panel into a shift, an order that runs over several shifts is stretched with the mouse, and a work order can be split by quantity. A line utilisation view shows how busy each line is, shift by shift. There is automatic plan optimisation too, but the planner has the final say: they review the proposal and adjust it with drag and drop.
An illustrative example
Three orders, two lines, loadings on Thursday and Friday. Every product needs one working day between production and loading. The example is made up, but it shows how the decisions are taken:
| Order | Loading | Production day | Line and shift | Why |
|---|---|---|---|---|
| Customer A, two products | Thursday | Wednesday | Line 1, shifts I and II | the job takes two shifts, so it occupies both |
| Customer B, one product | Friday | Thursday | Line 2, shift I | its packaging only arrives on Wednesday, so it can’t run earlier |
| Customer C, one product | Friday | Thursday | Line 1, shift I and Line 2, shift II | the quantity is split across two lines to finish the same day |
The production day follows from the loading date, the line and shift from line occupancy, and the final schedule from the material that is actually there.
Step 5: tell sales when you can deliver
Once all work orders for an order are scheduled, production knows when it will finish — the day of the last work order. That date has to reach sales before sales confirms a loading date to the customer. In NG Operations production does this through department sign-offs on the order itself: with its sign-off it records the date by which it can fulfil the order, and the proposed date is the day of the last work order in the plan. Who else signs off, and why sales shouldn’t promise a date alone, is covered in Confirming delivery dates.
Step 6: release work orders to the warehouse
A plan can exist weeks ahead, but for the warehouse it becomes real only when the work order reaches it. Good practice is to release work orders for today and tomorrow: early enough for the warehouse to stage material, late enough that they don’t have to be pulled back after every change to the plan.
In NG Operations work orders are sent to the warehouse with one click, and material is picked according to available stock or assigned automatically. The work order carries the planned consumption of raw materials and packaging, the planned output, location, lot and numbering. For the shop floor you print a production order with cartons, pallets, gross weight, the proposed lot and expiry date, customer instructions and photos.
The natural partner is NG WMS: when a work order is approved there, the material issue for production, the receipt from production and the return are created. NG Operations also works with the WMS you already run. The warehouse side is described in Warehouse management in manufacturing on the NG WMS blog.
Step 7: compare plan with actuals
A plan that is never compared with reality slowly turns into a document. After every shift, two things are worth seeing: how much material was actually issued against the plan, and how much was actually produced. The gap points either to a bill of materials that doesn’t match the shop floor, or to a problem on the line that needs fixing while it is still fresh.
In NG Operations actual issued and produced quantities come from the warehouse, with lot and location, and sit next to the plan on the work order, the production order and the customer order — as consumption and output bars, with no manual entry. When the plan breaks because of a breakdown or late material, you drag the work order to another day or shift instead of creating a new one. The wider picture comes from the production dashboards: output, kilograms per working day per line, utilisation, losses and scrap.
A production plan checklist
- Every job in the plan is tied to a customer order and its loading date.
- The production day is scheduled back from loading, in working days.
- The bill of materials is up to date, with loss and scrap allowances and packaging.
- Material shortages are visible per day, before a job goes onto a line.
- A job takes as many shifts as it really needs; large jobs are split by quantity.
- Sales gets the date from production before promising it to the customer.
- Work orders go to the warehouse for today and tomorrow, with a lot.
- Plan and actuals are compared every day, not at month end.
If your plan lives in a spreadsheet today, From Excel to ERP explains how to move to a system without disrupting the business, and MRP vs MPS vs APS shows where the production plan sits in the wider planning picture.
Frequently asked questions
What should a production plan contain?
For every job: the product and quantity, the line, day and shift, the customer order it is made for and that order’s loading date. It also helps to see whether the material is secured and what has been ordered but not yet scheduled.
How do you build a production plan by shift?
Jobs are placed on a grid where rows are lines, columns are days and each day is split into shifts. A job takes as many shifts as it really needs, and a large job is split by quantity across several shifts, days or lines.
How far ahead should production be planned?
At least as far as the longest material lead time — often printed packaging. The near days of the plan should be stable, because their material is already on order, while the later days let purchasing see requirements in time.
Can a production plan be run in Excel?
It can, while there are few orders and one person builds the plan. Problems start when sales, purchasing and the warehouse need to see the plan at the same time, when materials are calculated through bills of materials, and when actuals have to be copied back into the spreadsheet by hand.
Does NG Operations build the production plan by itself?
A wizard turns customer orders into production orders and work orders in one step, proposes the production day from the loading date and spreads the orders across shifts. There is automatic plan optimisation as well. The planner reviews the proposal and adjusts it with drag and drop.
How does the production plan reach the warehouse?
Work orders are released to the warehouse with one click — to NG WMS or to the WMS you already use. In NG WMS, approving a work order creates the material issue, the receipt from production and the return, and actual quantities flow back into NG Operations.
Want to see how this would look in your production?
In a free consultation and demo we walk through your sales plan, materials and production in NG Operations and show how the plan connects to the warehouse.