MRP vs MPS vs APS: what each one does and when you need it

Three acronyms that software brochures use almost interchangeably, even though they solve three different problems. We explain the order, the inputs and outputs of each layer, and how to tell which one you are actually missing.

In short

  • The MPS answers what to make and when, MRP answers how much material that takes and by when, and APS answers whether the plant can physically do it, and in what order.
  • The order is not optional: MRP running on a poor master schedule just orders the wrong materials faster.
  • Classic MRP assumes infinite capacity and fixed lead times — which is why plans look feasible on paper and fall apart on the shop floor.
  • Capacity-based scheduling only pays off once bills of materials, loss allowances and stock levels are accurate; otherwise it optimises the wrong numbers.
  • NG Operations covers the loop from the sales plan, through raw material and packaging planning, to a production plan by line, day and shift — the warehouse executes and actuals flow back into the plan.

Short answer: MRP, MPS and APS are not three names for the same thing. They are three layers of planning, each building on the one before. The MPS (master production schedule) decides what to make and when. MRP (material requirements planning) works out how much raw material, consumables and packaging that plan needs, and by when. APS (advanced planning and scheduling) checks whether the plant can actually do it, and in what order. Because each layer feeds on the previous one, the order matters: MRP running on a bad plan just orders the wrong materials faster. Mix the layers up and you end up buying a fix for a problem you don’t have, while the one you do have stays unsolved.

The easiest way to see the difference is one question per layer:

LayerThe question it answersMain inputMain output
MPS — Master Production ScheduleWhat should we make, and when?sales plan, confirmed orders, finished-goods stockproduction plan by product and period
MRP — Material Requirements PlanningHow much material does that take, and by when?master schedule, bills of materials, stock, open purchase orders, supplier lead timespurchase and order proposals
APS — Advanced Planning & SchedulingCan the plant do it, and in what order?orders, line and shift capacity, setup timesa schedule by resource and time

MPS: deciding what to make and when

The master production schedule is where commercial intent becomes a production commitment. It takes the sales forecast, confirmed orders and finished-goods stock and works out how much of each product to make in which week or month.

It sounds simple, yet this is where most of the gaps appear. If the sales plan lives in a spreadsheet that sales keeps editing, while production works from a copy that is weeks old, there is no master schedule — there are two plans colliding on the shop floor. A good MPS has three properties:

  • There is one valid plan. Everyone knows which version applies, who confirmed it and when.
  • The near horizon is frozen. The first weeks do not change without agreement, because their materials are already on order.
  • Known demand is kept apart from estimates. Confirmed orders are firm demand; the forecast only fills the gap above them.

In NG Operations this layer is fed by sales planning: customer orders and the remaining contracted quantities — contracted but not yet ordered — form the demand that purchasing and production see at the same time. Before a loading date is promised to a customer, purchasing, packaging, production and sales confirm it, and the system records who confirmed it and when. The plan stops being someone’s spreadsheet and becomes an agreement everyone can see.

MRP: from the plan to the purchase order

MRP is the oldest and most widespread layer. It takes the production plan, explodes each finished product through its bill of materials down to raw materials and packaging, subtracts what is in stock and what is on order but not yet received, and shifts the remainder back by the supplier’s lead time. The result is two lists: what to order and by when, and which orders to open.

That is a huge step up from calculating by hand — but only if the inputs are right. MRP does not create accuracy; it multiplies whatever accuracy you have. Three inputs decide everything:

  • The bill of materials and loss allowance. If the BOM ignores the waste and scrap that really happen on the line, MRP will order less than production uses — every time, on every item, without a single warning.
  • Stock levels. If stock is kept in one system while the goods in the warehouse lead a life of their own, the gap between paper and shelf turns into a shortage halfway through a batch.
  • Supplier lead times. If the lead time in the master data is shorter than the supplier really needs, the plan is late before it has even started.

In NG Operations this layer is the raw material planning and packaging planning screens. The shortage is calculated per day: demand from customer orders and the production plan, multiplied through the bill of materials and increased by the loss allowance, minus stock, goods in transit, open purchase orders and material already issued, plus a minimum stock level where one is set. A purchase planning wizard then turns the shortage into purchase orders grouped by supplier and delivery date. That step is covered in detail in From MRP proposal to purchase order, and the screens on the material requirements planning page.

Where classic MRP breaks down

MRP was born before computers could hold a model of the plant in memory, so it carries two simplifications that still cause trouble today.

First, it assumes infinite capacity. MRP will happily propose that Tuesday’s output be more than the line can produce in a full day. The plan is mathematically correct and physically impossible. So it looks tidy in the report, and the plant manager reworks it every morning by gut feel.

Second, it uses fixed lead times. A product gets one manufacturing lead time in the master data, and it applies whether the batch is small or large, and whether the line is empty or full. In reality the time depends on the quantity, on what ran on the line before and on how long changeover takes.

Anyone who has worked in manufacturing knows the result: the plan in the system and the plan on the whiteboard are not the same document. The moment that happens, the system stops being the source of truth and becomes a record that lags behind.

APS: planning that knows capacity runs out

Advanced planning and scheduling addresses exactly those two assumptions. APS takes the orders and places them on real resources — lines, machines, shifts and people — while respecting the constraints MRP cannot see:

  • the finite capacity of each resource, per shift and per day;
  • setup and cleaning time between batches, which depends on what ran before;
  • the sequence of operations in the process routing;
  • material availability at the moment the job is due to start.

The output of APS is not a list but a schedule: which job goes on which resource and when, and what moves if one of them stops. When a line goes down, a good schedule does more than say “the plan has failed” — it shows which orders are now late and which delivery dates are at risk.

This kind of planning makes sense once bills of materials, loss allowances and stock are already accurate and the real bottleneck is the sequence. As a first step it makes no sense: optimising inaccurate data produces a precisely wrong schedule, and produces it faster than before.

How to tell which layer you are missing

The symptoms are fairly clear if you read them honestly:

  • You are missing an MPS if production and sales work from different numbers, the plan changes by word of mouth and nobody can say which version is current.
  • You are missing MRP if purchasing orders by instinct and history, raw-material shortages surface on the day of production, and stock is too high on the wrong items and too low on the right ones — at the same time.
  • You are missing capacity scheduling if the plan exists and the material is there, yet delivery dates still slip, because the line schedule is made each morning on a whiteboard, from memory.

The most common mistake is skipping a layer. A company buys APS because deadlines are the problem, when the real cause is that there is no master schedule — so it ends up scheduling orders derived from a plan nobody trusts.

A rollout order that holds up

In practice the same sequence works every time, in phases rather than all at once:

  1. Clean up the data. Bills of materials, loss allowances, master data and real stock levels. This is the dull part, and it decides the outcome of the whole project.
  2. Introduce the master schedule. One plan, one valid version, visible to both sales and production.
  3. Switch on MRP. As a proposal the planner checks and confirms — not as a black box that orders on its own.
  4. Close the loop with actuals. Real consumption and scrap from the warehouse and the shop floor flow back into the plan and the bills of materials, so the next cycle calculates on reality rather than assumptions.
  5. Then capacity scheduling — if the bottleneck is still the sequence of jobs rather than the data.

Where NG Operations fits

NG Operations is built around that same sequence and covers the whole planning loop: the sales plan provides demand, raw material and packaging planning works out what to order, purchasing raises the purchase orders, and the production plan spreads the work across lines, days and shifts.

  • A plan by shift. The production plan is a grid of line × day × shift. Unplanned work is dragged into a shift, which creates a work order; an order can span several shifts and automatically skips weekends and public holidays.
  • From customer order to work order. A wizard turns a customer order into a production order and work orders in one step, proposes the production day from the loading date and spreads the orders across shifts.
  • Capacity in view. A line utilisation view shows how full each line is by shift, and automatic plan optimisation helps lay out the work. The planner adjusts by drag and drop and always has the final say.
  • Execution and actuals. Work orders are released to the warehouse in one click — NG WMS or another WMS — and the quantities actually issued and produced flow back into the plan with no manual entry, through the WMS and ERP integration.

The plan works at shift level, not as a minute-by-minute schedule of operations. For many plants that is exactly the level at which planning decisions are really made — and the level at which a plan stays manageable when orders change from one day to the next. How to build such a plan step by step is covered in How to build a production plan.

What rarely gets said

Manufacturers rarely lack a smarter algorithm. What they lack is a single source of truth and accurate inputs. A sophisticated optimiser running on a bill of materials nobody has updated in years will produce a schedule that is precise to the minute and wrong from day one.

That is why evaluating software should not start with “do you have APS?” but with “where do your bills of materials come from, and who changes them?” In NG Operations the bill of materials has versions with validity dates, so older orders remain explained by the recipe that applied at the time, and the production dashboards show yield, losses and scrap — so you can see whether the loss allowance in the BOM matches what really happens on the line. The answer to the bill-of-materials question predicts project success better than any feature list.

Frequently asked questions

Do I need APS if I already have MRP?

Only if your bottleneck is the schedule rather than the data. If delivery dates slip even though the material is there and the plan is clear, capacity scheduling addresses the real problem. If material shortages surface on the day of production, the cause lies in the data and in MRP, and APS will not help.

Can MRP work without accurate bills of materials?

Technically yes, in practice no. MRP multiplies the plan by the bill of materials, so every error in a quantity or loss allowance becomes a systematic error in every purchase order. Cleaning up BOMs is a prerequisite, not an afterthought.

What is the difference between an MPS and a sales plan?

A sales plan is an estimate of what will be sold. The MPS is a decision about what will be produced: it takes the sales plan, confirmed orders and finished-goods stock and turns them into a production commitment by product and period.

Why does MRP propose quantities the plant cannot keep up with?

Because classic MRP assumes infinite capacity and fixed lead times. It knows what needs to be made and when, but not how much a line can really produce. That is why the plan also has to be checked against capacity — by line, day and shift.

Does NG Operations do MRP and production planning?

Yes. Its raw material and packaging planning screens calculate the daily shortage from customer orders, the production plan and bills of materials, and a purchase planning wizard creates the purchase orders. The production plan assigns orders to lines, days and shifts, with a line utilisation view and automatic plan optimisation. It does not produce a minute-by-minute schedule of operations.

How long does a phased planning rollout take?

It depends on the state of your data more than on the software. When bills of materials and stock are accurate, the rollout moves faster; when they are not, cleaning up the data is the longest part of the project and cannot be skipped. You get the plan and timeline for an NG Operations rollout after an analysis of your processes.

Want to see how this would look in your production?

In a free consultation and demo we walk through your sales plan, materials and production in NG Operations and show how the plan connects to the warehouse.

More articles

  • Purchasing8 min read

    From MRP proposal to purchase order: pegging, quantities and approval

    An MRP run ends with a proposal, not a purchase order. We explain the four checks in between — cause, quantity, timing and approval — and what happens to the purchase order after it is confirmed, right through to goods receipt.

  • Production planning8 min read

    How to build a production plan: from customer order to a shift on the line

    A production plan answers one question: what gets made, on which line, on which day and in which shift, so the goods are ready for loading. Step by step, with an example: from demand and loading dates, through the bill of materials and material availability, to releasing work orders to the warehouse and comparing plan with actuals.

  • Manufacturing8 min read

    Bills of materials: the foundation of accurate product cost

    Product cost is only as accurate as the bills of materials and standard quantities behind it. On setting quantities as a share of net mass or per unit, loss and scrap allowances, the gap between standard and actual consumption, versions — and how a small error multiplies.