Confirming delivery dates: how to promise customers a date you can keep
Sales knows what the customer wants, but not whether the packaging will arrive or whether a line has a free shift. Why sales shouldn’t promise a loading date alone, what purchasing, packaging and production check first, and how department sign-offs and the loading plan keep the promise on paper and on the shop floor.
In short
- The date sales promises a customer depends on raw materials, packaging and a free shift — so raw-material purchasing, packaging purchasing and production confirm it before the promise is made.
- It pays to keep three dates apart: the one the customer requests, the one production can meet and the one finally agreed.
- Sales signs off last, once the customer accepts the date; the agreed date becomes the loading date that the production plan, purchasing and the warehouse work to.
- The loading plan shows how many loadings are already booked each day, which makes it the right place to check before offering a customer a date.
- In NG Operations every sign-off records who confirmed and when, and delivery notes go to the warehouse for execution, with shipped quantities flowing back.
Short answer: sales shouldn’t promise a delivery date alone, because it depends on things sales can’t see: whether raw materials arrive in time, whether there is packaging for that customer and whether a line has a free shift. So before the promise is made, raw-material purchasing, packaging purchasing and production each sign off on their part of the order, and sales signs off last, once the customer has accepted the date the others gave. The agreed date becomes the loading date that the production plan, purchasing and the warehouse all work to.
Why sales shouldn’t promise dates alone
Sales knows best what the customer wants and how much the date matters to them. But whether the date is possible, sales only finds out by asking others. When it doesn’t ask, the promise gets kept the hard way: rush purchases at higher prices, overtime, a partial shipment or a call to the customer saying the goods are late. Each of these costs money, and the last one costs trust as well.
The problem rarely comes from carelessness. It comes from each department seeing only its own part: sales sees the customer, purchasing the suppliers, production the lines. Confirming the date is where those views come together before the customer is given your word.
The opposite extreme is just as costly: sales that quotes distant dates to be on the safe side loses business, because the customer finds a supplier who can deliver sooner. The goal is not the latest safe date, but the earliest date that is genuinely possible.
Delivery date or loading date?
For a manufacturer, the date it really controls is the loading date — the day the goods leave your dock. The delivery date at the customer is the loading date plus transit time, and who arranges the transport depends on the agreed delivery terms. So it makes sense to confirm the loading date internally and derive the delivery date for the customer from it.
In practice it also pays to keep three versions of the same date apart:
| Date | Who gives it | What it means |
|---|---|---|
| Requested loading date | the customer | when the customer would like the goods |
| Date production can meet | production | when the goods will realistically be ready, according to the plan |
| Agreed loading date | sales, with the customer | the promise that binds every department |
When these three dates are kept separately, you always know what the customer asked for, what the plant could do and what was finally promised.
What raw-material purchasing checks
Raw-material purchasing answers one question: will the raw materials be in the warehouse before the production day? For a reliable answer it looks beyond current stock — at what is already promised to other orders, what is coming on open purchase orders and how long it takes to buy what is missing. If raw materials can’t arrive in time, that has to be said straight away; at that point there are still options — another supplier, a later date, or part of the quantity earlier.
In NG Operations purchasing sees an order’s requirement before signing off: raw-material planning calculates the daily shortage from all orders through the bill of materials, and material requirements planning turns it into purchase orders.
What packaging purchasing checks
Packaging is checked separately, because it is often customer-specific: their printed carton, label or film. Packaging purchasing confirms that packaging is available according to the bill of materials of the ordered products, or will be by the production day. With new or changed artwork this is often the decisive check, because printing takes time. How packaging is planned day by day is covered in Packaging planning in manufacturing.
What production checks
Production checks whether there is room in the plan: which line, on which day and in which shift can make the order. The most reliable answer is not an estimate but the plan itself — once the order’s work orders are scheduled, the day of the last work order is the day production finishes. On top of that, allow for the time between production and loading, for example for a lab analysis. Production that confirms from memory, without scheduling the work in the plan, can easily promise the same free day to two orders.
In NG Operations production records, with its sign-off, the date by which it can fulfil the order, and the proposed date is the day of the last work order in the production plan. That date is information for sales — on its own it doesn’t change the loading date. How the plan is built is covered in How to build a production plan.
Sales closes the loop
Once the other departments have signed off, sales has everything it needs for the conversation with the customer: what they asked for and when the goods can realistically be ready. If production’s date is later than the requested one, the customer is offered a realistic date rather than a hope. Sales signs off last — when the customer accepts the date — and at that point the agreed date becomes the order’s loading date.
In NG Operations the sales sign-off shows the requested loading date, the date on the order and the date production can meet, and proposes production’s date as the agreed date whenever it is later than the loading date. Signing off moves the order on the loading plan as well.
An illustrative example
On Monday a customer orders goods for loading on Wednesday of the following week. Raw-material purchasing signs off: the raw materials are in stock. Packaging purchasing checks the label printed for that customer — it arrives the following Monday, before production — so it signs off too. Production schedules the work orders on Tuesday and Wednesday, and since the product needs a day for lab analysis before loading, it records that it can fulfil the order by Thursday. Sales calls the customer and offers Thursday instead of Wednesday. The customer accepts, sales signs off, the agreed date becomes the loading date and the order moves from Wednesday to Thursday on the loading plan. The customer gets the goods a day later than requested, but on a date that will be kept — and knows it a week ahead, not on the day of loading.
Department sign-offs: who confirmed what, and when
A verbal “yes” has one flaw: a week later nobody remembers who said it. That is why every confirmation is worth recording, with a name and a time. A sign-off is not a formality: each department confirms only what it is responsible for, so when something breaks, you know where to look for the cause.
In NG Operations each customer order carries four department sign-offs: raw-material purchasing, packaging purchasing, production and sales. Each records who signed off and when, and can be withdrawn if circumstances change. Once raw-material purchasing, packaging purchasing and production have signed off, the order counts as promised goods, and by default the production planning wizard offers exactly such orders. The order list shows who has yet to sign off, and a dedicated filter picks out orders waiting only for sales — the list of customers to call.
The loading plan: how much work each day holds
Before offering a customer a date, it is worth looking at how many loadings are already booked for that day. The dock, the forklifts and the dispatch team have their own capacity; a day with too many loadings means delays even when the goods are ready. If Thursday is already full, offer the customer Friday.
In NG Operations the loading plan is a calendar of orders by loading date. You change a date by dragging the order to another day, and you can shift the loading date of several orders at once. Each loading card shows how much of the order has already shipped. Delivery notes go to the warehouse — NG WMS or another WMS — for execution, and shipped quantities flow back into NG Operations, so you can see what actually left. Documents and shipping are described on the Sales and delivery page.
When the date moves anyway
Even the best-confirmed date is not immune to a breakdown, a late supplier or a customer who changes their mind. What matters is that a change follows the same path as the confirmation:
- Tell the customer early. A new date is easier to accept a week ahead than the day before loading.
- Check with the departments again. The new date has to work for raw materials, packaging and production, just like the first one.
- Change the date in one place. When the loading date changes, material requirements and the production plan should follow — an order moved by a week moves the packaging and raw-material shortage with it.
- Don’t move what has already gone. Once the order is locked in the warehouse, its loading date can no longer change.
The same principle — one number for every department — is covered at the level of the monthly plan in S&OP in practice.
Frequently asked questions
Who should confirm a delivery date before it is promised to the customer?
Everyone who could put it at risk: raw-material purchasing, packaging purchasing and production. Sales signs off last, once the customer accepts the date the others gave.
What is the difference between a delivery date and a loading date?
The loading date is the day the goods leave your dock; the delivery date is the day they reach the customer — the loading date plus transit. A manufacturer directly controls the loading date, so that is what gets confirmed internally, and the delivery date for the customer is derived from it.
What if production can’t meet the date the customer asks for?
Production records the realistic date it can meet, and sales offers it to the customer. If the customer accepts, that becomes the agreed loading date; if not, you look for another solution — part of the quantity earlier, another line or a different schedule in the plan.
What is a loading plan?
A calendar of orders by loading date. It shows how many loadings are booked on each day, so you can see whether a day is already full before offering it to a customer. In NG Operations you change a loading date by dragging the order, and you can shift several orders at once.
What happens when the loading date moves?
Material requirements and the production plan should follow, because raw-material and packaging shortages are calculated by loading date. So a change should go through the same checks as the first date, and the customer should be told as early as possible.
Do department sign-offs slow sales down?
They shouldn’t. Instead of phone calls, each department sees on the order list what is waiting for its sign-off, and sales sees which orders are ready for a conversation with the customer. Each sign-off stays on record, so nobody argues later about who promised what.