From MRP proposal to purchase order: pegging, quantities and approval
An MRP run ends with a proposal, not a purchase order. We explain the four checks in between — cause, quantity, timing and approval — and what happens to the purchase order after it is confirmed, right through to goods receipt.
In short
- An MRP run produces a proposal; the purchase order only exists once a planner has checked and confirmed it.
- Before confirming, the planner needs four things: where the requirement comes from (pegging), how much really needs ordering, when the goods must arrive and who approves.
- Rounding up to minimum order quantities, pack sizes and pallets turns the surplus into stock — rounding rules are a business decision to agree with the supplier.
- In NG Operations a purchase planning wizard turns the shortage from raw material and packaging planning into purchase orders grouped by supplier and delivery date; one line can be split across several suppliers.
- Releasing the order to the WMS announces the delivery to the warehouse, and received quantities flow back to the purchase order and the plan with no manual entry.
Short answer: an MRP run does not end with a purchase order; it ends with a proposal. Between the two sit four questions the purchasing planner has to answer: why is this being ordered, how much really needs to be ordered, by when must it arrive, and who approves the order. Only once those four answers are clear does the proposal become a purchase order — which then goes to the supplier, announces the delivery to the warehouse and closes when the goods arrive. In NG Operations that path runs from the raw material and packaging planning screens, through the purchase planning wizard, to a purchase order released to the WMS. This article walks through the part of the journey that MRP stories usually skip.
Why MRP produces a proposal, not a purchase order
MRP calculates with the data it has: the plan, the bill of materials, stock, open purchase orders and lead times. It does not know that the supplier has announced a factory shutdown, that sales has verbally flagged a big order that is not in the plan yet, or that one raw material is about to be replaced by a substitute. So the division of labour makes sense: the system calculates, the planner checks and confirms.
In NG Operations that step is explicit. Material requirements planning works out what is missing and proposes quantities; in the purchase planning wizard the planner picks the exact item, the supplier and the delivery date, and only then confirms. That is the moment the purchase order is created — none goes out on its own.
Question one: why is this being ordered?
A proposed quantity on its own says nothing. A planner asked to confirm it needs to see where the requirement comes from: which customer order or production order, and for which day. That is pegging — the link between each requirement and the demand that caused it.
Pegging is not report decoration. It answers three very practical questions:
- Is the requirement backed by real demand? When you can see which order sits behind it, you can judge how certain it is and whether to order the full quantity now.
- What changes when the plan changes? When an order is moved or cancelled, you can see which requirements stem from it.
- What do you say when someone asks why? When finance or management asks why something is being bought, the answer is a link to the order, not a manual hunt through spreadsheets.
In NG Operations the planner chooses the demand sources — customer orders, the production plan or both — can isolate the requirements of a single customer, and can count only the orders that every department has already confirmed. A view by item or by customer drills the requirement down to the individual customer order, and the whole tree exports to Excel.
Question two: how much, really?
The gross requirement comes from exploding the plan through the bill of materials down to each raw material and packaging item, plus a loss allowance for the waste and scrap that really happen on the line. Subtract stock, goods in transit, open purchase orders and material already issued to production, and what is left is the net requirement — what is actually missing. A minimum stock level affects it too: where one is set, the shortage shows how much to order so that at least the minimum stays in stock. How to set that buffer without piling up goods is covered in How to reduce inventory without stopping production.
But the net requirement is often not the quantity you order. Suppliers have minimum order quantities, sell in packs and deliver on pallets, so the requirement gets rounded up. That creates a gap the planner has to understand, because every kilo above the requirement becomes stock.
| Step | What happens | What to watch |
|---|---|---|
| Net requirement | gross requirement minus stock, goods in transit, open purchase orders and material issued | whether stock and open orders are accurate |
| Minimum order quantity | if the requirement is below the supplier’s minimum, you order the minimum | whether the surplus gets used before it goes stale |
| Pack size | rounding up to a whole number of packs | how many packs end up opened |
| Transport unit | rounding up to a full pallet or truck | whether the freight saving is worth the extra stock |
The same requirement can turn into very different purchase orders depending on how the supplier delivers. The point is to decide about the surplus when you negotiate with the supplier — a smaller pack, a lower minimum — not by manually correcting every single order.
In NG Operations the proposed quantity is the full shortage, and packaging is proposed in whole units. When a supplier delivers in packs, the planner adjusts the quantity, and a remaining-quantity indicator immediately shows whether the shortage is covered, whether something is still missing, or whether more has been ordered than the shortage — which is allowed, but visible.
Question three: by when must it arrive?
A quantity without a date is only half an answer. Classic MRP works backwards: from the day the material is needed in production it subtracts the supplier’s lead time to get the latest day the purchase order must go out. If that day has already passed, it is the most important signal in the whole flow: either the plan arrived too late, or the lead time in the master data is more optimistic than reality. Either way, the planner has options today that will be gone tomorrow — another supplier, a partial delivery, or moving the order in agreement with production.
In NG Operations the shortage is shown per day on a calendar, alongside the purchase orders arranged by delivery date. Clicking a day shows what arrives that day and what is missing that day, and purchasing can plan only up to a chosen day — to cover the nearest loadings rather than the whole month. The planner sets the delivery date on the purchase order, as agreed with the supplier.
Lead times do not maintain themselves. The supplier card follows the chain contracted → ordered → received, and a supplier dashboard shows on-time and in-full deliveries, delays and lines still open past their due date. When a supplier is regularly late, you order from them earlier — otherwise the plan keeps calculating with a lead time that only holds on paper.
Question four: who approves, and what do they check?
Proposals are grouped by supplier and delivery date, because that is how ordering really works: one purchase order to one supplier, with several lines, for one delivery date. In the purchase planning wizard a single line can be split across suppliers — part from one, the rest from another — so that line ends up on two purchase orders. Before anything is created, a preview shows every future purchase order: supplier, date and lines with quantities.
The review does not have to take long if the planner knows what to look for:
- lines whose day of need is close — they need a decision today;
- lines where the ordered quantity is well above the shortage;
- lines driven by an order that was recently changed or moved;
- suppliers whose contract is about to expire, because a purchase order raised against a contract takes its items and prices from it.
Who may create, approve and confirm a purchase order is governed by roles and permissions by function, and every record shows who created it and who last changed it. Approval is an internal control: the purchase order becomes official and is locked against changes.
After approval: purchase order, contract and receipt announcement
A purchase order from the wizard is created with its supplier, lines and delivery date — nothing is retyped. When you order against a purchase contract, the purchase order takes the items and prices from the contract, and each line shows how much is still available under it; order more than that and the system warns you. The approved purchase order goes to the supplier as a PDF or Word document.
From then on the purchase order has a life of its own:
- Receipt announcement. When the goods are on their way, the purchase order is released to the WMS — in one click, for several orders at once if needed — and the warehouse gets an expected receipt from the supplier, carrying the purchase order number. With the link to NG WMS or another WMS, nobody retypes anything.
- Partial deliveries. The purchase order stays open until everything has arrived, and a received-quantity bar plus an ordered-versus-received comparison per line show what has arrived and what is still outstanding.
- Receipts flow back into the plan. Received quantities come from the warehouse, close the purchase order lines and reduce the shortage in the plan — with no manual entry.
- Invoice matching. Comparing what was ordered, received and invoiced (the so-called three-way match) happens where the books and payments are kept — usually in the ERP. That is why invoices should be matched against quantities actually received in the warehouse, not against estimates.
Where this flow usually breaks
When purchasing does not work as it should, the cause is rarely the MRP calculation itself. More often it is one of these breaks:
- Proposals get exported to a spreadsheet. The planner exports them, tidies them up in Excel and retypes them as purchase orders. The link to the cause is lost, and corrections made in the spreadsheet never make it back into the plan.
- Rush orders outside the plan. Purchasing orders “just in case”, and the next run sees it only as an open purchase order with no cause. Stock grows and nobody knows why.
- Dead open purchase orders. A purchase order whose goods will never arrive, left open, falsely covers the shortage — so what is really missing never gets ordered. Such orders should be closed or corrected.
- Outdated lead times. The lead time used in calculations no longer reflects how the supplier behaves, so delays are discovered at the loading dock.
- Rounding rules nobody revisits. Minimums and pack sizes agreed years ago still dictate how much goes into the warehouse.
Every one of these breaks has the same fix: proposal, purchase order, receipt and invoice must be links in one chain, not four documents in four systems.
The whole flow in NG Operations, step by step
- The requirement creates itself — from customer orders, the production plan and, for packaging, the remaining contracted quantities, through the bill of materials and the loss allowance.
- Shortage per day. Raw material and packaging planning show what is missing, when and how much, next to the purchase orders already on their way.
- The purchase planning wizard. The planner picks the item, supplier, quantity and delivery date; a line can be split across suppliers.
- Purchase orders by supplier and date. One supplier and one date make one purchase order; a preview shows what will be created before it is created.
- Approval and sending. The purchase order is approved and sent to the supplier as a PDF or Word document.
- Release to the WMS. The warehouse receives the expected delivery from the supplier.
- Actuals. Received quantities flow back to the purchase order and into the plan, and the shortage is recalculated.
The wider role of MRP in planning is explained in MRP vs MPS vs APS: what each one does and when you need it, and what makes packaging different in Packaging planning in manufacturing. If you would like to see how this flow would look with your own plan and bills of materials, book a demo.
Frequently asked questions
Why does MRP produce a proposal rather than a finished purchase order?
Because MRP only calculates with the data it has — the plan, bills of materials, stock, open purchase orders and lead times. The planner knows things the data does not show yet. In NG Operations the application calculates the shortage and proposes quantities, and the planner picks the item, supplier and delivery date in the purchase planning wizard before confirming.
What is pegging in purchase planning?
Pegging is the link between each material requirement and the order that caused it. It shows the planner why something is being bought, and when an order is moved or cancelled, which requirements stem from it. In NG Operations a view by item or by customer drills the requirement down to the individual customer order.
Why is the ordered quantity often higher than the net requirement?
Because the requirement is rounded up to the supplier’s minimum order quantity, pack size and transport unit. The surplus stays in stock, so rounding rules are worth revisiting with the supplier from time to time. In NG Operations the proposal is the full shortage, and a remaining-quantity indicator shows when more than that has been ordered.
Can one line be ordered from several suppliers?
Yes. In the purchase planning wizard a line can be split into parts, each with its own supplier, item, quantity and date. Parts are grouped by supplier and delivery date, so a split line ends up on two or more purchase orders.
What happens to a purchase order after it is confirmed?
It is approved and sent to the supplier as a PDF or Word document. When the goods are on their way, it is released to the WMS and the warehouse gets an expected receipt. The purchase order stays open until the last partial delivery, and received quantities flow back to it and into the plan. Invoice matching happens in the ERP.