Production KPIs that drive decisions: OEE and what goes with it
OEE is the most quoted figure on the shop floor and the most often misused — reduced to one number with no breakdown. How to break it down, where to measure it, and which indicators from planning and the warehouse belong next to it.
In short
- OEE is the product of availability, performance and quality, so the same overall figure can hide completely different problems with different solutions.
- Raising OEE on a machine that is not the bottleneck does not increase plant output — it only builds work in progress in front of the next operation.
- TEEP shows how much calendar time you use at all, while OEE shows how well you work in the time you have already planned.
- NG Operations shows what planning needs: plan versus actual, output per line, yield, losses and scrap — from data the warehouse sends.
- Every indicator needs an owner, a threshold and a decision; a number without them is not a KPI but decoration.
Short answer: OEE (overall equipment effectiveness) is the product of three factors: availability, performance and quality. As a single number it says almost nothing — it becomes useful only when broken down, measured at the bottleneck and owned by someone who knows what to do when it moves. OEE needs data from the machine itself: downtime, speed and the count of good units. Next to it belong indicators from planning and the warehouse — how much of the plan was done, output per line, yield and scrap — and they are often the first to show where the problem is.
OEE is not one number but three
OEE is probably the most quoted indicator in manufacturing. Almost every company that starts tracking the shop floor sooner or later arrives at it, and almost every one reduces it to a single number on a screen. On its own, that number is nearly useless, because the three factors are multiplied, not added. So OEE is never higher than its weakest component, and the same overall figure can describe a machine that keeps stopping but runs without defects and a machine that never stops but produces a lot of scrap. Those are two completely different problems with two different solutions, and the overall figure treats them as the same.
Availability measures how long the machine actually ran compared with the time planned for it. Performance measures whether the machine, while running, runs at its rated speed — this is where slow running and micro-stops hide, each lasting seconds but together eating a shift. Quality measures what share of output is right first time, without rework or rejection.
| Component | What it measures | Typical loss | Where the data comes from |
|---|---|---|---|
| Availability | How long the machine ran versus planned time | Breakdowns, waiting for material, long set-ups, unplanned stops | Downtime records from the machine or workstation, not estimates from memory |
| Performance | Whether the machine runs at rated speed while in operation | Slow running, micro-stops | Cycle counters and the machine’s rated speed |
| Quality | What share of output is right first time | Scrap, rework, rejected batches, start-up waste | Quality control and scrap records per order |
What hides behind each loss
The value of OEE lies not in the number but in the category of loss it points to. When availability drops, the question is not “what is our OEE?” but “why did the machine stop, and who fixes it?” A breakdown calls for maintenance, waiting for material calls for a better link with the warehouse and purchasing, a long set-up calls for work on changeovers. Three different departments and three different actions, all hiding behind the same availability figure.
The same goes for quality. Scrap at the start of a run, right after a changeover, is not the same problem as scrap that appears randomly throughout the shift. The first is a matter of settings, the second of the process or the incoming raw material. Add both into one “scrap rate” and you lose exactly the information that would tell you what to do.
One of those losses planning can prevent before it happens: waiting for material. When purchasing sees the raw-material and packaging shortage by day, and the warehouse receives the work order before the shift starts, the line stops less often because something “has not arrived”.
The trap: OEE on a machine that is not the bottleneck
The most expensive mistake with OEE is not inaccurate measurement but measuring in the wrong place. Put effort into raising OEE on a machine that is not the bottleneck and the plant’s output does not change by a single unit. All you get is a bigger pile of work in progress in front of the next operation, which still runs at its own pace.
Plant output is set by the bottleneck, not by the average of all machines. An hour gained at the bottleneck is an hour gained for the whole company; an hour gained anywhere else is usually just more expensive work in progress. So OEE should be tracked selectively. On machines with spare capacity, high OEE can even be a bad sign — a sign of producing to stock, regardless of the actual demand in the production plan.
OEE versus TEEP
TEEP (total effective equipment performance) asks a stricter question than OEE. OEE measures how well you work in the time you planned for the machine. TEEP measures how well you use all calendar time — every day and every shift. OEE does not penalise unplanned time; TEEP does.
That is why a machine can have excellent OEE and low TEEP: it runs brilliantly on one shift and stands idle the rest. For anyone considering new equipment, that is the key information — before investing in extra capacity, see how much of the existing capacity is not used at all. Sometimes opening a shift is cheaper than buying a machine, and TEEP shows that where OEE does not. Part of that question can be answered without measuring at the machine: in NG Operations the line utilisation view shows how many shifts per line are planned, so free capacity in the plan is visible at a glance.
Indicators that go with OEE
OEE describes equipment effectiveness, but a plant is more than equipment. To complete the picture, it needs indicators that measure plan adherence, yield and delivery to the customer:
- Plan adherence — how much of what was planned for the day was done, not just how much was produced in total.
- Output per line and per working day — what each line delivers when it runs, comparable across periods.
- Yield — how much finished product comes from the material issued; first-pass yield is a stricter measure, because it does not count what had to be reworked.
- Losses and scrap — by line and by cause, not as one figure for the whole plant.
- Changeover time — how long set-up between two runs takes, because hidden capacity often sits there.
- On time in full (OTIF) — what the customer actually feels; the same measure applies to suppliers.
- Planned versus actual consumption — comparing standard quantities with material actually issued, which shows whether bills of materials are accurate.
What NG Operations shows
OEE is calculated from machine data — downtime and speed. NG Operations, as a planning system, shows what can be seen from the plan and the warehouse, with no manual entry:
- Plan versus actual — on every released work order, a consumption bar (planned versus issued) and an output bar (planned versus produced), with data coming from the warehouse.
- Production — dashboards with quantities produced, kilograms per working day by line, yield, losses and scrap, compared with the previous period.
- Line utilisation — how many shifts per line are planned and where there is room.
- Dates — orders past their date and late purchase orders on the management warnings and risks dashboard, and supplier deliveries on time and in full.
For deeper analysis there is BI reporting, with export to Excel, PDF and Word. Looked at together, these figures often make the problem clear even without OEE: whether a line stands idle for lack of material, whether yield is falling on one line, or whether orders are late because the plan was overloaded.
Every number needs an owner and a decision
An indicator without an owner and a linked decision is not a KPI but decoration. Before any number goes on a screen, it should pass the same test:
- Who owns it? One name, not a department — the person who answers when the number goes wrong.
- Which decision depends on it? If the number moves, what concretely changes: who gets called, what stops, what gets moved.
- What is the threshold for action? Up to which value things are normal, and from which value action starts.
- Does the data come from a system? If the number is re-keyed by hand, it is late and wrong, and sooner or later nobody trusts it.
The quickest check is one question: when this moves, who does what? If there is no answer, the indicator does not belong in the operational view.
Operational dashboards versus presentation dashboards
A presentation dashboard is full of big numbers, upward trends and green tiles nobody uses for a decision. It looks good in a meeting and changes nothing on the shop floor. An operational dashboard is the opposite: it shows few numbers, but each has an owner, a threshold and a decision, and it is checked every day because people work from it.
The second split is about time. The operational view is for doing something today: what is late, what is missing for tomorrow’s orders, which loadings are due this week. Analysis looks back, by weeks and months, and serves decisions on capacity and investment. Both are needed, but mix them and you get dashboards too slow for operations and too shallow for analysis. In NG Operations the dashboards write their own insights — short sentences about what changed and what needs attention — so not everyone has to interpret the charts on their own.
Data has to be created where the event happens
The common denominator is where the data comes from. A number copied from a whiteboard at the end of the shift, yield estimated from memory and scrap rounded off by guesswork give figures that look convincing and have nothing to do with the plant. Data has to be created where the event happens — at the machine, in quality control, in the warehouse — and reach the system on its own.
For planning, the warehouse matters most. When NG Operations sends work orders to the warehouse and NG WMS returns the quantities actually issued and produced, with lot and location, plan versus actual and the dashboards are filled from the same data flow that runs production. How that connects to the ERP as well is described on the WMS and ERP integration page, and how to build a plan by line and shift in How to build a production plan.
Frequently asked questions
How is OEE calculated?
As the product of three factors: availability, performance and quality. Because they are multiplied, OEE is never higher than its weakest component, and the same overall figure can hide very different problems. That is why all three are tracked separately.
What is the difference between OEE and TEEP?
OEE measures how well you work in the time planned for the machine; TEEP measures how well you use all calendar time, including shifts when the machine stands idle. TEEP shows how much unused capacity you have before you consider new equipment.
Does it make sense to measure OEE on every machine?
Not equally. Plant output is set by the bottleneck, so OEE at the bottleneck is the most valuable, while raising OEE on a machine with spare capacity only builds work in progress.
Which production KPIs does NG Operations show?
OEE needs machine data — downtime and speed. NG Operations is a planning system and shows plan versus actual on work orders, output and kilograms per working day by line, yield, losses and scrap, line utilisation by shift and orders past their date — from data the warehouse sends.
Which indicators go with OEE?
Most often plan adherence, yield and first-pass yield, losses and scrap by cause, changeover time, on-time-in-full delivery and a comparison of planned and actual material consumption.
Why shouldn’t KPI data be re-keyed by hand?
Hand-copied numbers are late, contain errors and lose trust over time, so the dashboard stops being used for decisions. Data should be created where the event happens — at the machine, in quality control, in the warehouse — and reach the system on its own.